Passage through Powder Bridge Embankment on Prague Castle
ORDERING PARTY:
Prague Castle Administration
SUPPLIER:
Divize 5, Metrostav a.s.
Na Zatlance 1350/13, 150 00 Prague 5
Na Zatlance 1350/13, 150 00 Prague 5
DESIGNER:
AP Atelier - Křístek, Trčka a spol., s. r. o.
Metroprojekt, a. s.
Metroprojekt, a. s.
CONSTRUCTION DURATION:
04/2001 - 08/2002
INVESTING ORGANIZATION:
Dagmar a Václava Havlových VIZE 97
Prague Castle Administration
Prague Castle Administration
TECHNICAL DATA:
The Jelení Ditch used to be crossed over a wooden bridge on two walled pillars. In the 18th century, the bridge was destroyed and replaced with an earth-fill embankment. This divided the Jelení Ditch into the lower part and upper part. The goal of the ordering party was to renew the connection between the lower and upper part of the Jelení Ditch for walking visitors of the Prague castle.

The wings of both portals are made of monolithic concrete with juta fibre at the facing surface. The work included (besides the galleries and portals) also relocation and modification of the sewerage system, electrical connection, access road in the upper section and landscaping.
After the opening of the passage for public access it is possible to go from Klárov through the whole Jelení Ditch up to the Nový Svět while admiring unusual views of the Prague Castle.